Colchester City Council Preferred Options Local Plan Regulation 18 Consultation 2025

Search representations

Results for Tollgate Partnership Limited search

New search New search

Object

Colchester City Council Preferred Options Local Plan Regulation 18 Consultation 2025

Policy ST6: Colchester's Employment Needs

Representation ID: 13248

Received: 13/01/2026

Respondent: Tollgate Partnership Limited

Agent: NWS Planning Limited

Representation Summary:

The proposed allocation of Land South of Tollgate West for employment use does not acknowledge the potential for other uses (including a hotel or drive-through) to come forward on the Site. As such, even with the current permission built out, the scheme is unlikely to deliver all 3.7ha of the land within employment uses. There is also no certainty on delivery and indeed, in response to viability challenges relating to further employment floorspace, TPL are reviewing potential amendments to the permission consistent with the current District Centre designation. This would have the effect of further reducing the 3.7ha allocation.

Full text:

The proposed allocation of Land South of Tollgate West for employment use does not acknowledge the potential for other uses (including a hotel or drive-through) to come forward on the Site. As such, even with the current permission built out, the scheme is unlikely to deliver all 3.7ha of the land within employment uses. There is also no certainty on delivery and indeed, in response to viability challenges relating to further employment floorspace, TPL are reviewing potential amendments to the permission consistent with the current District Centre designation. This would have the effect of further reducing the 3.7ha allocation.

Object

Colchester City Council Preferred Options Local Plan Regulation 18 Consultation 2025

Policy PEP3 Land South of Tollgate West

Representation ID: 13253

Received: 13/01/2026

Respondent: Tollgate Partnership Limited

Agent: NWS Planning Limited

Representation Summary:

The proposed allocation of Land South of Tollgate West for employment use does not acknowledge the potential for other uses (including a hotel or drive-through) to come forward on the Site. As such, even with the current permission built out, the scheme is unlikely to deliver all 3.7ha of the land within employment uses. There is also no certainty on delivery and indeed, in response to viability challenges relating to further employment floorspace, TPL are reviewing potential amendments to the permission consistent with the current District Centre designation. This would have the effect of further reducing the 3.7ha allocation.

Full text:

The proposed allocation of Land South of Tollgate West for employment use does not acknowledge the potential for other uses (including a hotel or drive-through) to come forward on the Site. As such, even with the current permission built out, the scheme is unlikely to deliver all 3.7ha of the land within employment uses. There is also no certainty on delivery and indeed, in response to viability challenges relating to further employment floorspace, TPL are reviewing potential amendments to the permission consistent with the current District Centre designation. This would have the effect of further reducing the 3.7ha allocation.

Object

Colchester City Council Preferred Options Local Plan Regulation 18 Consultation 2025

Policy E4: Retail and Centres

Representation ID: 13258

Received: 13/01/2026

Respondent: Tollgate Partnership Limited

Agent: NWS Planning Limited

Representation Summary:

The application of criteria a) and b) to ‘in-centre’ proposals is also not consistent with the NPPF which ultimately directs proposals for main town centre uses towards defined centres. There is no sound basis on which to require in-centre proposals to justify their appropriateness within a town centre location.

Full text:

The application of criteria a) and b) to ‘in-centre’ proposals is also not consistent with the NPPF which ultimately directs proposals for main town centre uses towards defined centres. There is no sound basis on which to require in-centre proposals to justify their appropriateness within a town centre location.

Comment

Colchester City Council Preferred Options Local Plan Regulation 18 Consultation 2025

Policy EN3: Biodiversity and Geodiversity

Representation ID: 13267

Received: 13/01/2026

Respondent: Tollgate Partnership Limited

Agent: NWS Planning Limited

Representation Summary:

The Stanway Pits Local Wildlife Site (LoWS) designation on land to the south of Tollgate West is proposed to be carried forward as shown on the Preferred Options Local Plan Policies Map. This is not considered appropriate or justified on the basis that a large part of the area is now developed and the evidence base clearly states ‘the boundary of Stanway Pits will need to be updated again to reflect the development which has recently taken place within the centre and north east of the site’ (Appendix D, p.161). The LoWS designation on the Site therefore should be removed.

Full text:

The Stanway Pits Local Wildlife Site (LoWS) designation on land to the south of Tollgate West is proposed to be carried forward as shown on the Preferred Options Local Plan Policies Map. This is not considered appropriate or justified on the basis that a large part of the area is now developed and the evidence base clearly states ‘the boundary of Stanway Pits will need to be updated again to reflect the development which has recently taken place within the centre and north east of the site’ (Appendix D, p.161). The LoWS designation on the Site therefore should be removed.

For instructions on how to use the system and make comments, please see our help guide.